Construction of the new marine bridge near Thormøhlens gate 53A is entering a quieter phase. The contractor has completed the drilling of steel piles — the noisiest part of the project. In the coming weeks, minor excavation work will take place on the quay, along with concrete casting of the drilled steel piles and the land abutments for the bridge.
The actual bridge installation is scheduled for spring 2026.